Frame 3 turbine replacement
Nov 09, 2020
客户需要一个快速和成本效益的溶胶ution to replace two gas turbines approaching the designed life limit. Although they had two spare units from another manufacturer in their warehouse, they realized only a few months prior to installation that they couldn't be used due to weight, dimensions, and site constraints.
We quickly conducted an interchangeability study covering all instrumentation, combustion system, flange size, etc., and were able to supply two fully interchangeable turbines with safety service bulletins already completed.
We completed refurbishment activities, and delivered the units with three weeks to spare before outage start.